New Safe Confinement. Construction progress

$
0
0
Within the NSC Project at the construction site the following works are being performed: Assembly of the Arch metal structures (for 2nd lifting) According to the design – 4,097 tons 3,793.15 tons (92.58%) performed Installation of the Arch roof’s outer cladding Surface area of roof cladding before [...]